Prepare an exact-ratio or multi-unit transformer request
A useful first inquiry gives the required winding ratio, continuous MVA, quantity, accepted condition and site date. For multiple configurations, use one group per ratio and duty, then record documents and delivery scope against each offered unit.
What to include in an equipment purchase inquiry
Send the controlling specification and one-line, then fill any open items in this comparison. Mark unknown information as a question rather than assuming two quotations include the same scope.
| Check | Transformer | Switchgear or switchboard |
|---|---|---|
| Duty and identity | Listing ID or proposed manufacturer/model; GSU, step-down or distribution duty; quantity. | New build or identified lineup; equipment type; main/tie/feeder schedule; quantity. |
| Electrical ratings | All cooling-stage MVA/kVA, winding voltages, frequency, connections, taps, impedance and insulation. | Voltage, continuous current up to the specified rating, fault rating, breaker duty and control voltage. |
| Interfaces | Terminations, neutral, grounding, footprint, oil/fluid, cooling equipment and controls. | Transformer/generator interface, busway/cable entry, enclosure, interlocks, protection and controls. |
| Condition and records | Energization history, preservation, repair/rebuild scope, nameplate, drawings and matching tests. | Lineup and component identities, condition, breaker/relay schedules, drawings and tests. |
| Included scope | Bushings, radiators, fans, accessories, loose-shipped parts, preparation and loading. | Mains, tie, feeders, relays, metering, controls, auxiliaries and excluded equipment. |
| Commercial terms | Price basis, inspection, allocation, warranty provider/start date, freight and delivery milestone. | Price basis, approval drawings, build/release schedule, warranty, freight and installation boundaries. |
What belongs in an electrical equipment package RFQ?
List every equipment family you want priced, with one row per configuration. A transformer and switchboard package can include busway, UPS, batteries and bypass equipment, but none of those items should be left implied. Give the drawing reference, quantity, delivery phase and open requirements for each row.
- Dry-type transformer quotations
- Low-voltage switchboards and main-tie-main equipment
- Busway and bus duct route quotations
- UPS systems and critical power supply
| Equipment | Include in the inquiry | Make the scope explicit |
|---|---|---|
| Dry-type transformer | kVA, voltages, frequency, cast-resin/VPI requirement, cooling, winding specification and enclosure | Transformer, protection, accessories, drawings and agreed tests |
| Low-voltage switchboard | One-line, assembly rating, voltage, fault duty, main/tie/feeder schedule, controls and enclosure | Complete lineup, device quantities, interlocks, metering and connection equipment |
| Busway / bus duct | Route drawing, current, voltage, conductor, neutral/ground, straight lengths, fittings and tap-offs | Straight sections, feed connections, elbows, tap-off units, supports and transitions |
| UPS system | Required load in kW/kVA, voltage, runtime, battery requirement, redundancy, bypass and monitoring | UPS modules, battery equipment, cabinets, bypass, monitoring and quoted tests |
Make lineup quantities and project totals unambiguous
Write both the quantity per lineup and the total project quantity. Do not infer feeder quantities from the number of transformers. The following purchasing example records two requested lineups, each with two main breakers, one tie breaker and six feeders.
A usable inquiry says ‘12 feeders total: six per lineup’ and gives each device's required rating and function. State separately whether busway routes and tap-off devices are included. Counting devices does not establish the assembly rating, fault duty, operating sequence or technical suitability.
| Device scope | Per lineup | Lineups | Project total |
|---|---|---|---|
| Main breakers | 2 | 2 | 4 |
| Tie breakers | 1 | 2 | 2 |
| Feeder breakers | 6 | 2 | 12 |
Keep a drawing and interface register beside the price
Give each equipment tag a current drawing revision, connection boundary and responsible reviewer. Ask the supplier to identify the quoted model and any deviations. This makes it easier to compare equipment scope, documents and delivery dates without assuming that separate items connect as supplied.
For new OEM equipment, the 9-week delivery target starts after the PO, approved drawings and agreed commercial production release. The quotation confirms the equipment, quantity, factory allocation and destination. DDP delivery is included in that quotation; receiving, installation and commissioning remain separate unless included in writing.
For a first inquiry, email Tommy Marco at tommy@jjtransformers.com: ‘Equipment needed: [families]. Ratings and voltages: [requirements]. Quantities: [per configuration and project total]. Drawings: [references/revisions]. Destination and needed-on-site date: [details]. Open questions: [items to confirm].’ A short message is enough to start.
| Record | Information to retain |
|---|---|
| Equipment tag and quantity | Configuration group, number of complete assemblies, included devices and delivery phase |
| Drawing reference | One-line, layout or route reference; revision; approval status; open deviations |
| Connection boundary | Incoming and outgoing voltage, terminal/cable/bus arrangement, dimensions and supplied transitions |
| Acceptance record | Required drawings, model-specific evidence, agreed tests and the reviewer responsible for approval |
| Delivery boundary | Named destination, arrival milestone, DDP or other quoted scope, unloading and site-work responsibilities |
Compare shipment, delivery and commissioning separately
Ask which milestone each offered date describes: factory completion, seller release, ready for shipment, arrival at port, arrival at site or commissioning. Confirm inspection, packing, loading, freight, receiving and installation responsibilities. An unused description or historical test report does not establish present readiness or an active OEM warranty.
Review equipment and request a quotation
Contact Tommy Marco at 346-276-9540 or tommy@jjtransformers.com for specifications, price, current availability and delivery.
New Eaton equipment. 9-weeks total to your site.
For new manufacturing, J&J can quote Eaton pad-mounted and dry-type transformers up to 10 MVA / 10,000 kVA, medium-voltage switchgear, switchboards, breakers, busway, unit and prefabricated substations, and UPS systems. The 9-week total delivery window covers all listed OEM equipment through arrival at your site. Freight, import clearance and applicable import duties are included in the confirmed delivered quotation; the firm order schedule is confirmed in writing.
Step-down RFQ and acceptance evidence
Keep source/output voltages, required continuous duty, permitted operating direction and the offered nameplate ratings distinct in the equipment comparison. The step-down quotation checklist covers grounding, taps, impedance basis, protection, condition, records and included delivery scope. Send the available specification or nameplate directly to Tommy.
Common questions
Written quotes and supporting records control unit-specific ratings, availability, condition, price, and delivery.
Does this checklist replace the project engineering specification?
No. It helps organize procurement information. The responsible engineers and utility approve equipment suitability, applicable standards and the final project requirements.
Can one quotation cover transformers, switchboards, busway and UPS?
Yes. List each configuration, quantity, drawing reference and included scope separately. The quotation identifies the equipment offered, unresolved requirements, delivery phases and the responsible manufacturing entity for each item.
Does a delivered package mean everything is ready to energize?
Delivery identifies the agreed arrival milestone. Unloading, installation, field testing, commissioning and project approval are separate responsibilities unless expressly included in the written scope.