Review the published facts side by side. Matching a voltage or MVA rating does not establish compatibility. Ask your project engineer to review the complete unit records.
| Compare | 3 Rebuilt ABB 59.7 MVA-Class 230/13.8 kV TransformersJJ-ABB-230-13-3 | 167 MVA 230/34.5 kV Fortune Electric TransformerJJ-FORTUNE-230-167 |
|---|---|---|
| Manufacturer | ABB | Fortune Electric |
| Rating / output | 40/53.3 MVA at 55 C; 44.8/59.7 MVA at 65 C | 100/133/167 MVA; 35 MVA tertiary |
| Voltage / winding arrangement | 230 kV delta / 13.8 kV grounded wye | 230/34.5 kV with 13.3 kV buried-delta tertiary |
| Vector group | Delta–Grounded Wye; clock to confirm | YNyn0d1 |
| Frequency | 60 Hz | 60 Hz |
| Cooling | OA / FA / FA | ONAN / ONAF1 / ONAF2 |
| Impedance and base | 9.99% represented; MVA base not established | Not documented; confirm with J&J |
| Tap changer | Five-position HV DETC represented at 241.5, 235.75, 230, 224.25 and 218.5 kV | HV OLTC; 207–253 kV (±10%), design basis |
| Insulation / BIL | Not documented; confirm with J&J | HV line 750 kV; HV neutral and LV 200 kV; tertiary 110 kV |
| Quantity represented | 3 represented units | 1 unit |
| Technical details / open items | 1989 manufacture represented; three-phase, 60 Hz, copper windings; OA/FA/FA cooling, 55/65 C rise, and 9.99% represented impedance; HV taps represented at 241.5, 235.75, 230, 224.25, and 218.5 kV; Supplied equipment photo shown; request matching records, rebuild scope, tests and included accessories for all three units through J&J | Three-phase, 60 Hz; ONAN/ONAF1/ONAF2 cooling; 65 C winding rise; Grounded-wye / grounded-wye / delta; vector group YNyn0d1; HV OLTC range 207-253 kV; 13.3 kV, 35 MVA buried-delta tertiary; Copper windings, Type II mineral oil; Nameplate drawing identifies suitability for step-up operation; final test results and impedance available subject to confirmation |
| Evidence reviewed | Seller specification sheet and equipment photo reviewed | Nameplate drawing reviewed |
| Technical value basis | Seller specification and equipment photograph; confirm all three individual nameplates and rebuild records. | Supplied design nameplate and outline drawings; blank final values remain unconfirmed. |
| Details to confirm | All three matching nameplates, impedance bases, BIL and detailed rebuild scopes; Current inspection, tests, accessory completeness and individual transport dimensions/weights | Final tested impedance and base, manufacture year and final tap-switch specification; Final oil quantity, dimensions, tests, current preservation and complete accessories |
| Represented condition | Rebuilt; three ABB 230/13.8 kV transformers. Rebuild scope and included accessories are confirmed with the quotation | Brand new, never used and never energized |
| Equipment location | USA | USA |
| Technical records reviewed | 2026-10-08 | 2026-10-08 |
| Availability | Available; specification sheet reviewed; subject to prior sale and written reconfirmation | Available; subject to prior sale and written confirmation |
| Availability last confirmed | 2026-09-24 | 2026-09-24 |
| Shipping estimate | Request a written dispatch and delivery schedule | Request a written dispatch and delivery schedule |
| Nameplate reviewed | Not recorded as reviewed; request it | Yes — request the unit package |
| Drawings reviewed | Not recorded as reviewed; request them | Yes — request matching unit drawings |
| Factory test report reviewed | Not recorded as reviewed; request test records | Not recorded as reviewed; request test records |
| This unit only | Request more info | Request more info |
One request
Request Availability for Your Shortlist.
Email Tommy to discuss these options. The listing IDs will already be in the email subject.
What still needs to be checked?
Confirm frequency, cooling-stage ratings, impedance and its base, taps, vector group, grounding, BIL, site conditions and included scope against the project specification. A table cannot approve the fit.
Match the nameplate to the specification · Review surplus equipment records · Procurement checklist