Review the published facts side by side. Matching a voltage or MVA rating does not establish compatibility. Ask your project engineer to review the complete unit records.
| Compare | HICO 140 MVA 235/34.5/13.8 kV Transformer PairJJ-HICO-235-140-2 | Royal SMIT 525/69 kV Transformers — 3 AvailableJJ-SMIT-525-3 |
|---|---|---|
| Manufacturer | HICO | Royal SMIT |
| Rating / output | 85/115/140 MVA | 240/320/400 MVA; 250 MVA maximum step-down; 90 MVA tertiary |
| Voltage / winding arrangement | 235/34.5/13.8 kV | 525/69 kV with 13.7 kV buried-delta tertiary |
| Vector group | Winding connections and vector clock to confirm | YNyn0(d1) — Wye–Wye / buried Delta |
| Frequency | Not documented; confirm with J&J | 60 Hz |
| Cooling | ONAN / ONAF1 / ONAF2 represented | ONAN / ONAF / ONAF |
| Impedance and base | Not documented; confirm with J&J | H–X: 12.90% at 240 MVA, 525/69 kV, 85°C |
| Tap changer | Not documented; confirm with J&J | HV OLTC; 472.5–577.5 kV (±10%); 16 raise / 16 lower steps of 0.625% |
| Insulation / BIL | Not documented; confirm with J&J | HV winding 1550 kV / bushing 1675 kV; LV 350 kV; tertiary 150 kV |
| Quantity represented | 2 represented matching units | 3 units |
| Technical details / open items | The received offer represents a matching pair at 85/115/140 MVA, 235/34.5/13.8 kV, with copper windings, three phases and ONAN/ONAF1/ONAF2 cooling.; The exact offered high-side rating is 235 kV. Compatibility with a 230 kV project must be established from the actual nameplates, taps, insulation and project requirements.; An early-October arrival in the United States was scheduled in the earlier offer. Arrival has not been confirmed and the units are not described as immediately available U.S. stock.; Individual condition and service history are unresolved; the pair is excluded from the new/unused and used/pre-owned filters until confirmed.; Request both individual nameplates, frequency, winding connections, tertiary duty, tests, preservation/service records, arrival evidence and written purchase and warranty terms. | Three units offered for allocation; availability and 4–8 week shipping schedule confirmed by J&J on October 1, 2026.; Nameplate rating: 240/320/400 MVA with ONAN/ONAF/ONAF cooling. Maximum stated duty: 400 MVA step-up or 250 MVA step-down.; Three-phase, 60 Hz; 525 kV grounded-wye high side, 69 kV wye low side, and 13.7 kV buried-delta tertiary rated 90 MVA.; Copper windings; MR on-load tap changer; HV tap range 472.5–577.5 kV (±10%).; HV BIL: 1550 kV winding / 1675 kV bushing. LV BIL: 350 kV.; Nameplate H-X impedance: 12.90% at 240 MVA base, 525/69 kV, 85°C.; Supplied 2022 factory acceptance test report records Passed for the documented unit. Nameplate, outline drawing and test report available through J&J; match the records to all three units before purchase. |
| Evidence reviewed | Received written offer for a matching pair | Supplied nameplate, outline drawing and factory acceptance test report |
| Technical value basis | Written offer for a matching pair; confirm both actual nameplates. | Supplied nameplate for one documented unit; match the complete package to each of the three offered units. |
| Details to confirm | Both nameplates, current condition/arrival, frequency, rise, connections and tertiary duty; Impedance/base, BIL, taps, factory/service tests, preservation, dimensions/weights and accessories | Matching records for each offered unit, current condition, included accessories and transport scope; Unit-specific factory tests, present preservation and the step-down duty limit |
| Represented condition | Individual condition and service history require confirmation | 2022 manufacture shown in supplied nameplate; condition and service history confirmed with quotation |
| Equipment location | Location confirmed with quotation | International; dispatch location confirmed with quotation |
| Technical records reviewed | 2026-10-08 | 2026-10-08 |
| Availability | Early-October 2026 U.S. arrival was scheduled in the received offer; arrival and present allocation are unconfirmed | Immediately available; estimated 4–8 weeks to ship; subject to prior sale |
| Availability last confirmed | Request current confirmation | 2026-10-01 |
| Shipping estimate | Request a written dispatch and delivery schedule | 4–8 weeks to ship |
| Nameplate reviewed | Not recorded as reviewed; request it | Yes — request the unit package |
| Drawings reviewed | Not recorded as reviewed; request them | Yes — request matching unit drawings |
| Factory test report reviewed | Not recorded as reviewed; request test records | Report reviewed; confirm matching records for each unit |
| This unit only | Email for specs & price | Email for specs & price |
One request
Request Availability for Your Shortlist.
Email Tommy to discuss these options. The listing IDs will already be in the email subject.
What still needs to be checked?
Confirm frequency, cooling-stage ratings, impedance and its base, taps, vector group, grounding, BIL, site conditions and included scope against the project specification. A table cannot approve the fit.
Match the nameplate to the specification · Review surplus equipment records · Procurement checklist